Hindustan Petroleum Corporation Ltd. and Ors. v. Puri Hp Centre
Case brief
What is this about?
This judgment addresses six arbitration cases where the petitioners sought an extension of the Sole Arbitrator's mandate under Section 29A(4). The court allowed the extension by six months due to sufficient cause, including pandemic and monsoon delays, with mutual party consent.
What did the court decide?
Extension of the Sole Arbitrator's mandate by six months, until 14.12.2024.