What is this about?
In this writ petition under Article 226, the petitioner sought recovery of unpaid contractual dues of Rs. 6.42 crore. The High Court, finding no evidence of material dispute regarding work completion, directed the State respondents to pay the balance amount within three months along with interest at 7% p.a. in case of default.
What did the court decide?
The State respondents directed to release the outstanding payment of Rs. 6.42 crore within 3 calendar months (by 31.07.2025).