Mainuddin v. the State of Assam and 6 Ors.
Case brief
What is this about?
Contractor's unpaid admitted bill for flood-control works under the Assam Water Resources Department was sought to be recovered on the pattern of an earlier writ matter. Court found the liability admitted by the State and directed payment within five months.
What did the court decide?
Respondents to pay petitioner's outstanding admitted amount of Rs. 15,69,002/- within 5 months; directions of WP(C) 4734/2021 applied.