M/S Tkj Infrastructure Pvt. Ltd. v. the National Hydro Electric Power Corporation Private Limited and 5 Ors.
Case brief
What is this about?
The petitioner, declared L1 bidder, was subjected to an additional performance security demand not in the tender. After cancellation, the bidder agreed to the extra security. The court directed respondents to withdraw the cancellation and award the work.
What did the court decide?
Direction to respondents to withdraw cancellation order and award the work to the petitioner.