M/S Trikuta Enterprise v. the State of Assam and 2 Ors.
Case brief
What is this about?
Syndicate Bench allowed a writ petition claiming payment for works under a terminated public contract. It distinguished a prior order by another coordinate bench due to delay and specific factual circumstances, but directed automated measurement of executed work and subsequent payment within six months.
What did the court decide?
Direction to measure executed work quantity and pay the petitioner the determined amount within six months.