Pradip Kumar Das v. the State of Assam and 6 Ors.
Case brief
What is this about?
Contractor sought payment of Rs.21,75,376 contractual dues for road improvement work under the PWD, unpaid because his name was missing from the original chronological liability list. The Court found the claim genuine on the parawise comments and disposed of the petition directing further verification and payment within three months.
What did the court decide?
Direction to Chief Engineer, PWD Roads to verify petitioner's claim and pay admitted dues within three months.