M/S Karbi Projects Private Limited v. the State of Assam and 5 Ors.
Case brief
What is this about?
A contractor sought payment of balance contractual dues for road works under the NLCPR scheme despite a completion certificate. Finding serious disputed questions of fact requiring evidence and an arbitration clause in the contract, the High Court dismissed the writ petition with liberty to invoke arbitration.
What did the court decide?
Writ petition dismissed; petitioner given liberty to invoke the arbitration clause in the contract agreement.