Nabajyoti Das v. Union of India and 5 Ors.
Case brief
What is this about?
A registered contractor sought payment of balance amounts due on completed flood-protection work contracts. Liability statements admitted part of the claim. Relying on the Nazim Hussain precedent and party consent, the court directed re-verification by the Chief Engineer and compliance with earlier directions within five months.
What did the court decide?
Direction for re-verification of admitted liability and payment per Nazim Hussain directions, entire process within 5 months.