Aftab Hussain v. Union of India and 5 Ors.
Case brief
What is this about?
A registered Water Resources contractor sought payment of an outstanding balance of Rs.9,51,389 for completed works. With respondents consenting and a liability statement issued by the Executive Engineer, the Court disposed of the petition at motion stage directing re-verification and release of dues per earlier directions.
What did the court decide?
Petition disposed at motion stage with directions to verify and pay admitted dues of Rs.9,51,389 per prior Nazim Hussain directives within 5 months.