Beaver Infra Consultants Pvt. Ltd. v. the Union of India and 2 Ors.
Case brief
What is this about?
Petitioner sought appointment of a sole arbitrator under Section 11(6) for disputes over unpaid final bill and extra-work claims exceeding the contract value. The contract's Clause 10.1 barred arbitration for claims above 20% of contract value. Holding the claim manifestly non-arbitrable on prima facie scrutiny, the court dismissed the petition.