M/s Nayak Infrastructure Pvt. Ltd. v. the State of Ap and 5 Ors.
Case brief
What is this about?
Petitioner sought payment for executed road construction work. Respondents cited withholding due to public complaints and SIT case registration. Court noted respondents did not deny petitioner's Bill of ₹8.03 crore and directed payment.
What did the court decide?
Direction to release payment of Rs. 8,03,08,354/- for the executed work within one month of the receipt of the certified copy.