Manaj Kr. Brahma v. the State of Assam and 5 Ors.
Case brief
What is this about?
The petitioner, a contractor, sought writ relief for outstanding dues of Rs. 19.8 lakhs for completed work. The Court directed the respondent Bodoland Territorial Council to examine and verify the claim under its existing order of 15.11.2021 within the stipulated six-month period and release the amount if admissible.
What did the court decide?
Directed the respondent BTC authorities to complete the verification of the petitioner's claim within the stipulated time frame and release the amount if found admissible.