Tulunga Narzary v. the State of Assam and 5 Ors.
Case brief
What is this about?
Petitioner sought payment of Rs. 15 lakh for completed road work. Court disposed of writ petition by relying on a prior decision dated 17.12.2021.
Petitioner sought payment of Rs. 15 lakh for completed road work. Court disposed of writ petition by relying on a prior decision dated 17.12.2021.
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
Page No.# 1/3
GAHC010037322022
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/1621/2022
TULUNGA NARZARY
S/O- LATE BIREN NARZARY, R/O- SARAIBIL, P.S- GOSSAIGAON, DISTKOKRAJHAR, BTR, ASSAM
VERSUS
THE STATE OF ASSAM AND 5 ORS REPRESENTED BY THE COMMISSIONER AND SECRETARY TO THE , GOVT OF ASSAM, PUBLIC WORKS, DEPARTMENT (ROADS) DISPUR GUWAHATI 06
2:THE CHIEF ENGINEER P.W.D.(ROADS) ASSAM CHANDMARI GUWAHATI- 03
3:THE BODOLAND TERRITORIAL COUNCIL REP. BY THE SECY. BTC P.O AND DISTRICT-KOKRAJHAR ASSAM PIN- 783370
4:THE ADDL. CHIEF ENGINEER CUM DIRECTOR PWD THE BODOLAND TERRITORIAL COUNCIL BTC P.O AND DISTRICT- KOKRAJHAR ASSAM PIN-783370
5:THE DIRECTOR
Page No.# 2/3
PANCHAYAT AND RURAL DEVELOPMENT DEPARTMENT THE BODOLAND TERRITORIAL COUNCIL BTC P.O AND DISTRICT- KOKRAJHAR ASSAM PIN-783370 6:THE BLOCK DEVELOPMENT OFFICER DOTMA DEVELOPMENT BLOCK DOTMA P.O- DOTMA DIST- KOKRAJHAR ASSAM PIN- 78334
Advocate for the Petitioner : MR R DHAR
Advocate for the Respondent : SC, P AND R.D.
BEFORE
HON’BLE MR. JUSTICE MANASH RANJAN PATHAK
ORDER
07-03-2022
Heard Mr. R. Dhar, learned counsel for the petitioner and Mr. D. Nath, learned Senior Government Advocate, Assam as well as Standing counsel, PWD (Roads) for the respondent No.1. Also heard Mr. S. R. Rabha, learned Standing counsel, BTC for the respondent Nos. 2 to 6.
The respondent authorities in the BTC, PWD (Roads) Department by the Completion Certificate (Annexure 8 to this petition) specified that the petitioner has completed the work of ‘Construction of new Road with Earth filling and Sand Gravelling from Ramakand L.P. School to Dakhina House along with 1 No. Box type Culvert at No.1 Matiapara’ under SOPD fund for the year 2018-19.
It is stated by the petitioner that though he completed the work, noted above, the respondent authorities did not pay him the admitted amount of Rs. 15,00,000/-.
Learned counsels for the parties submitted at the Bar that the issue involved in this writ
Page No.# 3/3
petition is covered by the decision of this Court dated 17.12.2021, passed in WP(C) No. 6079/2021.
In view of the above, this writ petition is disposed of in terms of the order dated 17.12.2021, passed in WP(C) No. 6079/2021.
JUDGE
Comparing Assistant
Colour shows how this judgement treated each authority
WP(C) No. 6079/2021Referred¶26
Tulunga Narzary
State of Assam
Commissioner and Secretary to the Govt of Assam, PWD (Roads)
Chief Engineer P.W.D.(Roads) Assam
Bodoland Territorial Council
Addl. Chief Engineer cum Director PWD BTC
Manash Ranjan Pathak
As recorded by the court registry