Domon Longmailai v. the State of Assam and 5 Ors.
Case brief
What is this about?
Petitioner, a registered contractor, sought directions for disbursement of final bills for completed road work under a Public Works Department contract. The court, noting non-payment despite verified completion and a pending supplementary demand, disposed of the petition by directing respondent authorities to examine the claim within 45 days.
What did the court decide?
Petitioner directed to submit order; Respondents vide 2 and 3 to examine claim within 45 days and process it in light of TamsherAli principles.