Central Bank of India v. M/s Chandra Engineering Works
Case brief
What is this about?
The Debts Recovery Tribunal adjudicated an application under Section 19 of the RDPA seeking recovery of a loan defaulting amount and interest, determining the debt and ordering its realization.
What did the court decide?
The debt of Rs. 57,82,609/ along with interest at 8.50% p.a., pendent-lite and costs was determined and ordered to be recovered from the respondents jointly and severally.