Canara Bank v. M/s. Modern and General Enterprises
Case brief
What is this about?
The tribunal allowed the bank's original application for recovery of a loan default. It held that business losses due to the pandemic could not absolve the borrower of liability despite a seven-year gap between default and application, directing recovery of principal, interest, and costs.
What did the court decide?
Order to pay Rs.28,27,029/-, future interest at 8.75% p.a., and costs; Recovery Certificate issued.