The Debt Recovery Tribunal rejected the defendants' belated objection regarding the bank's interest rate, holding it was an agreed term. The court allowed the application for an outstanding sum of approximately Rs. 80.74 lakh, awarding interest at 10% p.a. instead of the contractual rate.
What did the court decide?
Defendants jointly and severally directed to pay Rs. 80,73,945.25 with further interest @ 10% p.a. from 25.08.2015 till realization.