Punjab National Bank (Oriental Bank of Commerce) v. M/S Vijaya Ganapaty Papers Rep by Its Prop Mrs v Prasannakumari
Case brief
What is this about?
Debt Recovery Tribunal allowed the applicant bank's application for condonation of 98 days delay in re-presenting the original application due to misplaced documents, conditioning approval on future consideration of interest claims for the default period.
What did the court decide?
Application for condonation of 98 days delay allowed; consideration of interest claim for the deferred period to be deferred till issuance of Recovery Certificate.