Premlata Khakaria and Ors. v. Icici Bank Ltd. and Anr.
Case brief
What is this about?
The Appellate Tribunal noted defects in an appeal filed under section 18 of the SARFAESI Act, including omission of an event list, failure to submit a pre-deposit, and incorrect citation of interim orders. The appellant was directed to remove these defects within 15 days.
What did the court decide?
Appellant directed to remove defects within 15 days failing which application liable for rejection.
What the court decided
IN THE DEBTS RECOVERY APPELLATE TRIBUNAL AT KOLKATA
DY. no.121/2022 Date: 04/05/2022
Mrs. Premlata Kharkia & Ors...………...Appellant
Vs.
ICICI Bank & Anr.... .……….Respondents
Received an application under section 18 of the Securitisation & Reconstruction Of financial Assets & Enforcement of Security Interest Act,2002 presented by Ld. Advocate, Ms. Jayati Chowdhury.
Scrutiny of the application observed the followings:
The application has been filed on behalf of Mrs. Premlata Kharkia & Ors against the order passed by the Ld. Presiding Officer, DRT-3, Kolkata order dated 04-02-2022 in SA/33/2017. Application fees of Rs.11005/- vide T.R. no.115621 dt.02-05-2022 has been paid along with the application.
The case is under the jurisdiction of this Appellate Tribunal.
The Application is well within the period of Limitation in terms of Hon’ble Supreme Court Order.
The Waiver application is filed.
Issues for consideration
1 issue framed by the court
Whether the appeal filed under section 18 of the SARFAESI Act is barred due to defects in the application, including missing list of dates and events, non-filing of deposit, and incorrect mention of i
Parties & counsel
- appellant
Mrs. Premlata Kharkia & Ors
- respondent
ICICI Bank & Anr
Case details
As recorded by the court registry
- Court
- DRAT
- Decided on
- · May
- CNR
- 191090001212022
- Topic
- Banking and Recovery
All orders in this case
9 orders share this CNR
Similar cases