Gazi Enterprise v. State Bank of India
Case brief
What is this about?
The Debt Recovery Appellate Tribunal condoned a delay in filing the appeal due to inadvertent loss of the impugned judgment copy and reserved the hearing of an application for waiver from pre-deposit.
What did the court decide?
Condonation of delay in filing appeal in I.A. 170 of 2022 allowed.
What the court decided
IN THE DEBTS RECOVERY APPELLATE TRIBUNAL AT KOLKATA
(Appl. Dy. No. 169 of 2022)
(Arising out of TS.A. 85 of 2016 in DRT-3 Kolkata) THE HON’BLE MR. JUSTICE ANIL KUMAR SRIVASTAVA CHAIRPERSON
21.11.2022
M/s. Gazi Enterprise
-Vs-
State Bank of India & Anr.
… Respondents
Mr. S. Ganguly, ld. Counsel with Mr. T. K. Mukhopadhyay, ld. Counsel for the appellant.
Mr. P. K. Roy, ld. Counsel for the respondent.
THE APPELLATE TRIBUNAL :
I.A. Dy. No. 170 of 2022 has been filed by the appellant praying for condonation of delay in filing the appeal. Impugned judgement was passed on 08.03.2022 while the appeal was filed on 25.05.2022. Learned counsel for the appellant submits that owing to inadvertence the clerk of the learned advocate copy of the impugned judgement was misplaced and it was ultimately traced out and appeal was preferred.
Parties & counsel
- appellant
M/s. Gazi Enterprise
- respondent
State Bank of India
Coram
Anil Kumar Srivastava
Case details
As recorded by the court registry
- Court
- DRAT
- Decided on
- · November
- CNR
- 191090001692022
- Topic
- Banking and Recovery
All orders in this case
7 orders share this CNR
Similar cases