Amit Engineers v. Chief Rolling Stock Engineer (Coach), Northern Railway
Case brief
What is this about?
O.M.P.(MISC.)(COMM.) 34/2026 & I.A. 570/2026, High Court of Delhi, Justice Avneesh Jhingan, order dated 12.01.2026. Petition filed under Section 29A of the Arbitration & Conciliation Act, 1996 by Amit Engineers (advs.: Ms. Minakshi, Ms. Shakshi) against Chief Rolling Stock Engineer (Coach), Northern Railway (advs.: Mr. Sushil Kumar Pandey, SPC, with Mr. Raj Kumar, SO) seeking extension of the period for concluding arbitration proceedings. Respondent's counsel raised no serious objection; time for conclusion of proceedings extended up to 31.03.2026; petition disposed of accordingly. No precedents cited; no monetary amount awarded.
What did the court decide?
Extension of the time period for conclusion of the arbitration proceedings up to 31.03.2026. ¶4