M/S Lnj Power Ventures Limited v. M/S Rswm Ltd.
Case brief
What is this about?
Section 29A Arbitration & Conciliation Act 1996; extension of period for concluding arbitration proceedings; three-month extension; draft award prepared and circulated to Co-Arbitrators; O.M.P.(MISC.)(COMM.) 24/2026 & I.A. 351/2026; M/s LNJ Power Ventures Limited v M/s RSWM Ltd; High Court of Delhi; Hon'ble Mr. Justice Avneesh Jhingan; order dated 08.01.2026; petition disposed of.
What did the court decide?
Time period for conclusion of the arbitration proceedings extended by three months. ¶16