Shri Subhash v. Delhi Development Authority DDA & Ors.
Case brief
What is this about?
Contempt petition alleging DDA failed to carry out demolition ordered in an earlier writ. DDA showed demolition programmes were executed; petitioner produced photographs showing remaining structures. Court directed DDA to comply with the earlier order regarding those photographs within four weeks and disposed of the contempt.
What did the court decide?
DDA directed to comply with order dated 15.05.2024 with respect to petitioner's photographs expeditiously, within 4 weeks; petitioner may revive contempt if no action taken.