Sepc Limited Earlier Known as Shirarm Epc Limited India v. Steel Authority of India Limited & Anr.
Case brief
What is this about?
Section 9 Arbitration and Conciliation Act 1996 post-award interim measure; performance bank guarantee invoked and encashed; unlawful encashment; Steel Authority of India Limited v SEPC Limited (earlier Shirarm EPC Limited India); Arbitral Award dated 20.02.2026 notified 24.02.2026; Section 34 objections ninety (90) days; PBG valid till 28.02.2026; deposit with Registrar General; interest-bearing account; release subject to further directions; Durgapur Steel Plant Medium Structural Mill Contract Agreement 11.05.2010; State Bank of India letters 24.02.2026; E-mail 10.03.2026 money released; O.M.P.(I)(COMM.) 92/2026 & I.A. 6232/2026; Mini Pushkarna, J.; order dated 12.03.2026; petition disposed of.
What did the court decide?
Interim measures under Section 9 of the Arbitration Act: respondent no. 1 directed to deposit the encashed Performance Bank Guarantee amount of Rs. 5,40,00,000/- with the Registrar General of this Court within six (06) weeks; the deposited amount to be kept in an interest-bearing account; directions regarding release subject to further orders of the Court. The petition along with pending application I.A. 6232/2026 disposed of accordingly.