Ms. Stalagmite Infracon Pvt. v. Ms. Ashray Homes Build Well Pvt.
Case brief
What is this about?
S.34 Arbitration Act petition dismissed as barred by limitation (Delhi HC, Mini Pushkarna J., O.M.P.(COMM) 367/2019, dec. 07-04-2026). Interim award deciding all but one claim is challengeable under S.34; S.34(3) limitation (3 months + max 30 days) strict and inflexible; awaiting balance award not sufficient cause. Condonation refused for 30-day filing delay and 90-day re-filing delay: nine re-filings of identical 701-page petition with unremoved defects = pretence/misuse of process; 701→2622 pages showed last-day filing aimed to circumvent limitation; bulky-record plea frivolous; petition also non-est. Relied on: IFFCO v. Bhadra Products (2018) 2 SCC 534; State of A.P. v. Damani Constructions (2007) 10 SCC 742; Basawaraj (2013) 14 SCC 81; Shivamma (2025 SCC OnLine SC 1969). Award quantum mentioned: Rs. 6,31,674/- + 9% p.a.
What did the court decide?
Awaiting the award on the remaining claim is not an acceptable justification for condoning the 30-day filing delay, because the impugned interim Award had decided all but one of the petitioner's claims, thereby deciding the disputes substantially between the parties.