M/S a S Patel v. National Highway Authority of India
Case brief
What is this about?
Section 9 Arbitration and Conciliation Act 1996 interim relief; NHAI performance security surety bond invocation Rs. 3,31,46,877 (bonds 2123005625510000002, 2123005625510000003); demand letters 05.03.2026 and 27.03.2026; deductions from interim payments; IPC No. 5 unprocessed; Clause 25 conditions of contract; SAROD arbitration; Section 17 application before Arbitral Tribunal; prior petition O.M.P.(I) (COMM.) 90/2026 order dated 20.03.2026; O.M.P.(I) (COMM.) 146/2026; Mini Pushkarna J; petition disposed of with directions to arbitrate.
What did the court decide?
The interim injunction sought against invocation of the performance security surety bonds was not granted; the petition was disposed of with directions to the parties to approach the nominated arbitrators for appointment of the Presiding Arbitrator under SAROD Arbitration, and with liberty to the petitioner to raise all its issues, including the Section 9 submissions, before the Arbitral Tribunal in an application under Section 17 of the Arbitration Act.