Public Works Department Education West Division (N) through Executive Engineer v. M/S Tewatia Construction Private Limited through Its Director
Case brief
What is this about?
O.M.P.(COMM) 111/2024 | Delhi High Court | Section 34 Arbitration and Conciliation Act 1996 | unilateral appointment of sole arbitrator | Section 12(5) proviso 'express agreement in writing' | no deemed/conduct-based waiver; participation and non-objection inconsequential | Clause 25(ii) GCC; Chief Engineer (Projects) PWD GNCTD; letter dated 10.06.2022 | Seventh Schedule ineligibility | Arbitration and Conciliation (Amendment) Act 2015 | award set aside (~Rs. 2.5 crore plus interest) | deposit with Registrar General released to petitioner within four weeks | Bhadra International (2026) SCC OnLine SC 7; Bharat Broadband (2019) 5 SCC 755; CREST/CORE Constitution Bench (2025) 4 SCC 641 | Justice Harish Vaidyanathan Shankar | decision 29.04.2026.
What did the court decide?
Petition allowed and Impugned Arbitral Award set aside; the amount deposited with the Registrar General (with interest accrued) to be released to the Petitioner within four weeks; setting aside does not preclude parties from pursuing remedies available in law; pending application(s), if any, disposed of accordingly.