Dristti Structural Engineering Pvt. Ltd. v. National Highways Authority of India
Case brief
What is this about?
Contractor sought Section 9 interim relief against an NHAI liquidated damages notice. Parties agreed the disputes would go to the already constituted Arbitral Tribunal; the Court dispensed with Section 21 notice, referred the disputes to that tribunal, converted the petition into a Section 17 application, and disposed of it.