Ada Buildwell Infratech LLP v. Simplex Infrastructures Limited
Case brief
What is this about?
Section 11(6) Arbitration and Conciliation Act 1996; appointment of Sole Arbitrator; Letter of Intent dated 10.11.2017; Clause 14 arbitration clause; seat New Delhi; Section 21 notice dated 25.02.2025 unanswered; Section 12(2) disclosure within two weeks; Delhi International Arbitration Centre (DIAC) aegis and Schedule of Fees; ADA Buildwell Infratech LLP v. Simplex Infrastructures Limited; ARB.P. 676/2026; 'The Ultima' Sector-81 Gurugram project; stone, marble and granite works; claim Rs.13,00,862/-; petition disposed of.
What did the court decide?
Appointment of Mr. Kaustubh Rai, Advocate, as Sole Arbitrator to adjudicate the disputes between the parties; arbitration to be conducted under the aegis of DIAC with fees per DIAC Schedule of Fees; all rights and contentions kept open. ¶¶23