Renew Urja Shachar Pvt. Ltd. v. Central Transmission Utility of India Ltd. & Ors.
Case brief
What is this about?
Renew Urja Shachar Pvt Ltd v Central Transmission Utility of India Ltd (CTUIL) & Ors., W.P.(C) 19757/2025, High Court of Delhi, Amit Bansal J, order 07.01.2026: writ petition disposed with time-limited status quo protecting petitioner's 300 MW wind-project connectivity (Ujjain, MP) under Connectivity Agreement dated 22.03.2024 and its bank guarantees from precipitative action by CTUIL, pending CERC hearing of interim-stay application sought for 13.01.2026; no opinion on merits; no statutes or cases cited.
What did the court decide?
Interim status quo maintained: respondent no.1 (CTUIL) restrained from taking precipitative steps or action qua the bank guarantees furnished by the petitioner and qua the connectivity granted under the Connectivity Agreement dated 22 March 2024, for a limited period till CERC takes up and considers the matter; CERC requested to hear the petitioner's interim-stay application on 13 January 2026 or shortly thereafter, and left free to consider whether continuation of the interim direction is warranted.