Devendra Singh v. the Bses & Ors.
Case brief
What is this about?
Keywords: BSES electricity connection refused; new connection denial; TF Technical Feasibility inspection 28.11.2023; no dwelling unit; demolished front side; no separate kitchen; MCD action unauthorised construction; outstanding dues other meters; CGRF BSES complaint dismissed 22.08.2024; Ombudsman NCT Delhi appeal dismissed 03.04.2025; MCD NOC requirement; ownership documents chain; Khasra No. 556 Nizamuddin West; Waqf/DDA land claim; ASI protected monuments; 'Parivartan' case Delhi HC; liberty fresh application after rebuild; premises not fit for connection; Amit Bansal J; W.P.(C) 11973/2025; decided 15.04.2026.
What did the court decide?
Petition dismissed, but petitioner given liberty to seek a fresh electricity connection from BSES after rebuilding the subject premises with a proper kitchen; BSES to consider such application in accordance with applicable rules and regulations. All pending applications disposed of.