Lokesh v. Vice Chairman, Delhi Development Authority & Ors.
Case brief
What is this about?
DDA Housing Scheme 2008; Draw No.136 dated 16.12.2008; Scheduled Caste category allottees; demand-cum-allotment letter withheld; FIR naming petitioners; EOW investigation; letter no. 423/P.Sec/Addl.CP/EOW dated 29.10.2009; chargesheet 2019 listing petitioners as witnesses only; no charges framed; source of funds outside DDA's domain; Article 226 writ of mandamus; Delhi High Court; Jasmeet Singh J; directions to issue demand-cum-allotment letter within 8 weeks; LIG flats at Dwarka Sector 18-B and Vasant Kunj; petitions allowed and disposed of; recall clause.
What did the court decide?
Petitions allowed: DDA to issue demand-cum-allotment letters within 8 weeks indicating the amount due and payable; payment within 8 weeks thereafter; on payment, petitioners to be allotted their flats as per entitlement. DDA entitled to seek recall of the order if any of the statements is found untrue. Petitions disposed of along with pending applications.