Energy Efficiency Services Limited v. a One Realtors Pvt. Ltd.
Case brief
What is this about?
Section 29A Arbitration and Conciliation Act 1996; extension of arbitral mandate after expiry of twelve-month/six-month period; Section 29A(4) read with Section 29A(5); Rohan Builders (India) Private Limited v. Berger Paints India Limited, 2024 SCC OnLine SC 2494; mandate extended till 11.08.2025; Sole Arbitrator appointed 31.03.2022 in CS(COMM) 610/2019; pleadings completed 21.02.2023; mutual six-month extension ended 19.08.2024; evidence complete, final arguments stage; Energy Efficiency Services Limited v. A One Realtors Pvt Ltd; O.M.P.(MISC.)(COMM.) 931/2024; Delhi High Court; Subramonium Prasad J; disposed 17.01.2025.
What did the court decide?
Mandate of the Sole Arbitrator extended till 11.08.2025 for pronouncement of the award; petition disposed of along with pending applications, if any. ¶¶20