Afcons Infrastructure Ltd. v. Ircon International Ltd.
Case brief
What is this about?
Keywords: extension of arbitrator's/arbitral mandate; Section 29A(4) and (5); Arbitration and Conciliation Act 1996; expired mandate 09.09.2025; reserved award; consent of parties; six-month extension from 10.09.2025; notice accepted, respondent consented; Delhi High Court; Justice Jyoti Singh; AFCONS Infrastructure Ltd. (petitioner); IRCON International Ltd. (respondent); petition allowed and disposed of.
What did the court decide?
Extension of the mandate of the learned Arbitral Tribunal by 06 months from 10.09.2025, enabling it to pronounce and publish the reserved award; petition allowed and disposed of. ¶¶13