Mcnally Bharat Engineering Company Limited v. NTPC Limited
Case brief
What is this about?
Extension of arbitral tribunal term under Section 29A(4) Arbitration and Conciliation Act 1996; six-month extension w.e.f. 25.12.2024 after expiry of mutually consented S.29A(3) extension; three-member AT; submissions complete, clarifications pending; no objection by parties; insolvency proceedings against petitioner McNally Bharat Engineering Company Limited; respondent NTPC Limited; I.A. 1429/2025 infructuous; Anish Dayal J; High Court of Delhi; O.M.P.(MISC.)(COMM.) 61/2025; order dated 20.01.2025.
What did the court decide?
Extension of the term of the Arbitral Tribunal for six (6) months w.e.f. 25 December 2024; pending application rendered infructuous. ¶¶19