Power Grid Corporation of India Ltd. v. Spml Infra Limited
Case brief
What is this about?
Arbitration and Conciliation Act 1996 - S.29A(4)/(5) extension of arbitral mandate maintainable even after expiry of S.29A(1)/(3) period (Rohan Builders and Ajay Protech followed); Power Grid Corporation of India Ltd v. SPML Infra Ltd; O.M.P.(MISC.)(COMM.) 564/2023 and O.M.P.(T)(COMM.) 136/2024; mandate extended till 31.12.2025 subject to Fourth Schedule fees fixed on 02.08.2018; substitution of Presiding Arbitrator under S.14(1)(a)/S.15 refused - apprehension of bias is not de jure inability, remedy lies under Ss.12/13 before the Tribunal and thereafter S.34 (HRD Corporation followed; Bharat Broadband referred); unilateral fee enhancement foreclosed by Coordinate Bench judgment dated 27.11.2024 in O.M.P.(MISC.)(COMM.) 286/2023; Kaimur Arbitration; RGGVY Package D1 Rohtas Bihar; Justice Deepak Verma (Retd.); decided 17.04.2025 by Sachin Datta, J.
What did the court decide?
O.M.P.(T)(COMM.) 136/2024 (substitution of the Presiding Arbitrator under Section 14(1)(a) read with Section 15) dismissed; O.M.P.(MISC.)(COMM.) 564/2023 allowed: time for completion of the arbitral proceedings and making of the arbitral award extended till 31.12.2025, subject to the Arbitral Tribunal continuing at the fees initially agreed on 02.08.2018 (Fourth Schedule). Both petitions disposed of in these terms.