Solar Optimised Line Private Limited through Shri Ankit Grover Director v. India Sme Technology Services Limited
Case brief
What is this about?
Section 29A(4) Arbitration and Conciliation Act 1996; extension of arbitral tribunal mandate after expiry on 28.02.2025; six-month extension to make and publish Arbitral Award; regularisation of expired mandate period; Delhi High Court; Jasmeet Singh J.; O.M.P.(MISC.)(COMM.) 288/2025; Solar Optimised Line Private Limited vs India SME Technology Services Limited; award pending pronouncement; voluminous pleadings delay.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal by six months to make and publish the Arbitral Award; the intervening period from 28.02.2025 till the date of the order (15.04.2025) regularised. ¶19