Delhi High Court, O.M.P.(MISC.)(COMM.) 521/2025, decided 15.07.2025 by Jyoti Singh, J. Joint consent petition under Section 29A(4) and (5), Arbitration and Conciliation Act 1996, by M/s Amar Construction and Govt. of NCT of Delhi for extension of the Sole Arbitrator's mandate by 9 months from 21.06.2025 in respect of arbitration arising from Agreement dated 14.02.2019 (construction of 30 additional SPS hostel rooms and allied works at KISS Issapur, New Delhi); earlier extension of six months upto 20.06.2025; pleadings complete; petition allowed and disposed. No precedents cited; no monetary quantum.
What did the court decide?
Mandate of the Sole Arbitrator extended by nine months from 21.06.2025; petition allowed and disposed of in the aforesaid terms. ¶¶22