Nhpc Ltd. v. V3S Infratrech Ltd.
Case brief
What is this about?
Appeal against rejection of Section 34 challenge where the award was filed two days beyond the 120-day period. The Division Bench held the filing non-est per Pragati Construction, refused to entertain the new counsel's-mistake ground, noting NHPC's dedicated Arbitration Cell, and dismissed the appeal.