Ircon International Limited v. Reacon Engineers (India) Pvt. Ltd.
Case brief
What is this about?
Full Bench of Delhi High Court held that while the initial filing of an arbitration petition was not non est, a subsequent voluminous re-filing due to defects amounted to a fresh filing beyond the statutory limitation period, dismissing the appeal under Section 34 of the Arbitration and Conciliation Act, 1996.
What did the court decide?
The instant appeal along with pending application(s) stands dismissed.