M/S Spml Infra Limite v. Mis Bhavani Enterprises through Proprietor Ravi Kumar Rathod
Arbitration and Conciliation Act, 1996 – Sections 34 and 37
Case brief
What is this about?
FAO (COMM) 250/2025; Delhi High Court; SPML Infra Limited v. M/s Bhavani Enterprises; Arbitration and Conciliation Act 1996 Section 34 Section 37; challenge to order setting aside arbitral award dated 30.03.2024 in part; limitation; separability of claims; Work Order dated 25.09.2011; Work Order No. SIILlMBMCIWOI 13-141001-00 dated 10.10.2013; 5% retention from RA bills; Defect Liability Period; termination of contract 09.04.2019; invocation of arbitration 27.12.2019; MBMC Mira Bhyander Municipal Corporation subcontract; perverse finding standard; scope of Section 37 appeal narrower than Section 34; Somdatt Builders-NCC-NEC(JV) v. NHAI Civil Appeal No. 2058/2012; counter claim not pressed; appeal dismissed, no costs.
What did the court decide?
Claim no.1 was within limitation: the work order was terminated on 09.04.2019 and the disputes relating to the retained 5% of the RA bills crystallised only at that point (the 5% being payable only after successful completion/expiry of DLP), so respondent no.1 was within its right to invoke arbitration on 27.12.2019.