Smt. Kamlesh Dudeja v. M/S Aryan Bagga Associates Pvt. Ltd. & Ors.
Case brief
What is this about?
O.M.P.(I) (COMM.) 357/2025; High Court of Delhi at New Delhi; order dated 04.11.2025; Justice Purushaindra Kumar Kaurav. Petitioner: Smt. Kamlesh Dudeja (counsel: Kirti Uppal, Sr. Adv., with Naveen Sharma, Ayushi Agarwal). Respondents: M/s Aryan Bagga Associates Pvt Ltd & Ors. (counsel: Tanveer Ahmed Mir, Sr. Adv., with Prateek, Talaj, Aditya, Chaitanya, Daksh). Subject: interim protection under arbitration proceedings; petition disposed of, remaining prayers converted to application under Section 17 of Arbitration and Conciliation Act, 1996 to be dealt with by the Arbitrator; interim arrangements of 17.09.2025 (property-inspection co-operation for loan purposes, bar on creating third-party rights, Court permission needed to finalise loan) continue during its pendency.
What did the court decide?
The interim arrangements directed on 17.09.2025 (respondents to co-operate for inspection of the property if intended to obtain loan by the petitioner; respondents not to create any third-party right; petitioner or her representatives not to finalise availment of loan without Court permission) remain in force during the pendency of the application under Section 17 of the A&C Act.