Rajesh Kumar v. Ajay Kumar @ Ajay Singh
Case brief
What is this about?
CM(M) 316/2023 Delhi High Court Manoj Jain 08.07.2025 condonation of delay written statement commercial suit 120 days outer limit SCG Contracts India Private Limited Chamankar Infrastructure (2019) 12 SCC 2010 Section 105 CPC liberty ground of objection memorandum of appeal trial completed final arguments extraordinary jurisdiction declined disposed Delhi Legal Services Authority Shahdara legal aid counsel timeline inflexible sensitization Secretary DSLSA restoration dismissed in default 20.02.2024 restored 07.05.2025 recovery Rs.5,42,449.35 Rs.8 lacs father-in-law son-in-law not a precedent
What did the court decide?
Petition disposed of without interference with the impugned order dated 07.01.2023 condoning the delay in filing the written statement; liberty reserved to the petitioner to challenge that order as a ground of objection in the memorandum of appeal if the Trial Court dismisses his suit (per Section 105 CPC); copy of the order directed to be sent to the learned Secretary, Delhi State Legal Services Authority to sensitize panel counsel about adherence to prescribed timelines; order declared not a precedent.