M/S Richa Constructions Co. v. M/S Nbcc (India) Ltd.
Case brief
What is this about?
Restoration of Section 34 Arbitration and Conciliation Act objections dismissed in default; condonation of delay without formal condonation application; seven-month delay in restoration application; dismissal due to counsel's illness; PSU litigant and diligence; Commercial Courts Act timelines argument; Article 227 scope - quantum of costs not examined; costs Rs. 7,500/-; merits over defaults; CM(M) 1864/2024; Richa Constructions Co vs NBCC (India) Ltd; Justice Girish Kathpalia; Delhi High Court; order upheld, petition dismissed.
What did the court decide?
There is no requirement of a formal application for condonation of delay in filing any application or appeal; if the court is satisfied from the record about the circumstances that led to the delay, it can condone the delay and adjudicate upon the main application. ¶¶30