M/S M.S. Contractor Thr. Proprietor Mr. Manmeet Singh v. Union of India & Anr.
Arbitration & Conciliation Act – Sections 11, 21 and 12(2)
Case brief
What is this about?
Delhi High Court, ARB.P. 265/2025, decided 07.02.2025 by Justice Subramonium Prasad. Section 11 Arbitration & Conciliation Act petition by M/S M.S. Contractor (proprietor Manmeet Singh) against Union of India & Anr. Railway parking contract (cycles, scooters, cars, buses, trucks, tempos) at Delhi first entry Railway Station; payment disputes from March 2020 COVID-19 onset; Section 21 notice dated 27.05.2024 unanswered; Clause 27 arbitration clause undisputed; Arundhati Katju, Senior Advocate appointed Sole Arbitrator; DIAC-administered arbitration; DIAC fee schedule; Section 12(2) disclosure; claims and counter-claims left open. Keywords: Section 11 appointment, Section 21 notice, Section 12(2) disclosure, DIAC, railway parking contract, COVID-19 payment disputes.
What did the court decide?
Sole Arbitrator appointed (Ms. Arundhati Katju, Senior Advocate) to adjudicate the disputes; arbitration under the aegis of DIAC with fees per DIAC Schedule; disclosure under Section 12(2) directed; rights and contentions kept open; petition disposed of along with pending application(s), if any.