R S Infraprojects Pvt. Ltd. v. Power Grid Corporation of India Ltd.
Case brief
What is this about?
W.P.(C) 222/2025; R S Infraprojects Pvt Ltd v. Power Grid Corporation of India Ltd; High Court of Delhi; Justice Sachin Datta; order dated 10.01.2025; blacklisting/debarment; Clause 2.1 of Instructions to Bidders (ITB); one-year non-responsive/not eligible declaration; termination of contract dated 02.01.2025; notice of default dated 25.11.2024 under Clause 36.2.2 GCC; petitioner's reply dated 29.11.2024; natural justice; opportunity of hearing; undertaking to withdraw/keep in abeyance debarment; dismissal as withdrawn with liberty; preservation of arbitration and damages claims; bank guarantee invocation; Substation Extension Package SS-110; Specification No. CC/NT/WAIS/DOM/A06/23/01910; WBSETCL/CESC/CSPTCL consultancy; Eastern Region Expansion Scheme-XXXII; CM APPL.1097/2025 (Stay) and CM APPL.1098/2025 (Exemption) disposed.
What did the court decide?
Petition dismissed as withdrawn with liberty: petitioner may assail the contract termination and other measures (including invocation of bank guarantee and damages for wrongful termination) in appropriate proceedings including arbitration, and may resist any fresh debarment action under Clause 2.1 ITB; respondent's Clause 2.1 invocation withdrawn/kept in abeyance, with any fresh notice to be accompanied by opportunity of reply and hearing per natural justice.