M/S Nhpc Ltd. v. M/S Jaiprakash Associates Ltd.
Case brief
What is this about?
Execution petition against a corrected arbitral award whose Rs. 60 crore component was set aside under two Section 34 petitions. The court held the counter-claim of Rs. 13,24,03,428 in favour of the decree-holder remained independently enforceable as a decree and allowed execution.
What did the court decide?
Decree-holder entitled to execute/recover Rs. 13,24,03,428; amount to be adjusted from dues payable to judgment-debtor under Vivad Se Vishwas Scheme II; interest issue left open.