M/S Shri Ram Electrical Works v. Power Grid Corporation of India Ltd.
Case brief
What is this about?
Petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of the Arbitrator's mandate. The Court found sufficient cause shown and allowed the extension for three months from 01.12.2024, subject to filing legible copies of documents.
What did the court decide?
Mandate of the learned Arbitrator extended for a period of three months from 01.12.2024.