Religare Finvest Limited v. Konti Infrapower and Multiventures Private Limited and Ors.
Case brief
What is this about?
The Delhi High Court allowed applications seeking an extension of time under Section 29A(4) and (5) of the Arbitration and Conciliation Act, 1996. The court extended the period for completing arbitral proceedings and making an award jointly requested by counsel.
What did the court decide?
The time period for completion of arbitral proceedings and making of arbitral award is extended till 01.12.2025.