What is this about?
Delhi High Court extended the mandate of an Arbitral Tribunal for six months under Section 29A of the Arbitration Act, 1996 to allow the tribunal to pronounce an award after final arguments concluded.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal for a further period of six months.